The building process at Largo-CR Homes makes it possible for our customers to stay focused on the fun and exciting prospect of building a new home while we deal with the more mundane aspects of costing, permitting and code review. Our process is simple. A customer typically comes to us with an idea for a new home that may have come from our website, or may be an amalgamation of inspirations from many sources. It may even be just a narrative description of what is wanted in a new home. One of our experienced designers takes over from there, and our long term expertise in construction logistics allows us to address these issues while the customer continues to concentrate on the creative side.

1. EXPLORATORY

  • Review our Portfolio for inspiration
  • Begin financial discussions with a lender
  • Meet with the Owner of Largo-CR Homes
  • Receive a Largo-CR Homes quote, including specifications and allowances
  • Timeline: 8-10 Months

2. CONTRACTUAL

  • Execute Contract

3. DESIGN PHASE

  • Start Design Phase
  • Approve Floorplans
  • Approve Elevations
  • Complete Plans
  • Timeline: 4 Weeks

4. PLAN REVIEW/PERMITTING

  • Submit Plans for Architectural Review Board Approval
  • Submit Plans for Permits
  • Timeline: 4-5 Weeks

5. SELECTION PROCESS

  • Establish a schedule as to when the Selection Process should begin. This process will take 3 days to complete
  • Once timeframe is established, Owner and Design Coordinator, Cheryl Rymal, will begin to schedule appointments for countertops, cabinets, plumbing fixtures, appliances, flooring and bath tile, decorative lighting fixtures, front door and door hardware selections
  • Cheryl will accompany each customer on their appointments to assist and make recommendations, while keeping the customer within budget, throughout the entire selection process
  • Approximately two weeks later, the quotes for the selections the customer made will come in. Customer will review the quotes and approve or make any necessary changes
  • Once all the quotes have been approved, and prices agreed upon, construction begins
  • Timeline: 2 ½ weeks